In line with the 2026-2027 Strategic Plan announced last March, Energía Aljaval reaffirms its execution capacity in Mexico by successfully overcoming one of the sector’s most demanding regulatory barriers. The company announces that four of its solar photovoltaic macro-projects in the state of Coahuila have advanced to the next phase within the Second Call for Priority Attention issued by the Ministry of Energy (SENER).
This milestone confirms the viability and maturity of Energía Aljaval’s portfolio. As a sign of firm commitment to the advancement of the pipeline, the company and its partners have already formalized the payment of the fees corresponding to the interconnection studies before the National Energy Control Center (CENACE), securing their strategic position in the grid.
The Coahuila block: A high-impact energy cluster
The four projects pre-qualified by SENER total a combined capacity of nearly 900 MWdc, consolidating Coahuila as one of the country’s major poles for renewable development to meet the growing industrial demand driven by nearshoring. The assets that make up this block are:
-
San Francisco: 372.1 MWp
-
San Isidro: 344.1 MWp
-
Gómez Farías: 113.8 MWp
-
Chapote: 83.6 MWp
CENACE is expected to issue the results of these updated connection studies before September 10, 2026. Once the final technical and economic viability is confirmed, along with the imminent obtaining of the generation permits from the National Energy Commission (CNE), these four parks will be positioned as one of the most attractive and secure private portfolios in the Mexican market.
Consolidation of strategic alliances and capital attraction
The success in this regulatory process has been driven by the solid co-development alliance forged with Nisa Energy, a strategic partner that has strengthened the financial and operational structure of the projects, guaranteeing compliance with strict government schedules.
With the development risk mitigated and the main administrative milestones passed, Energía Aljaval has initiated advanced negotiations with top-tier international infrastructure consortiums and institutional investors. The objective is to structure the sale or final partnership for these projects under a Ready-to-Build (RTB) or advanced As-Is modality, ensuring the capital injection necessary to take these 900 MW to their construction phase and subsequent Commercial Operation Date (COD).
“The advancement of our projects in Coahuila within SENER’s binding planning is not a future promise; it is a documented reality,” emphasizes Energía Aljaval’s Management. “We have demonstrated that our reading of the new regulatory framework was correct. Today, with the CENACE studies paid and in progress, and backed by high-capacity partners like Nisa Energy, we are ready to deliver to large offtakers and global investors the megawatts of clean and firm energy that the industry in Mexico urgently demands.”